Earlier this week, the Dierks school board received an update on the proposed elementary school classroom building project from the construction manager Michael McGrew of Clark Construction.

McGrew reported a six room project would cost the district approximately $1.75 million and would take about eight months to complete. He also presented cost estimates to construct four rooms or five rooms. McGrew said the district would only save about $300,000 if they built four classrooms instead of six.

Dierks Superintendent Jody Cowart reported the district would have about $300,000 left over from the bond funds for other district projects. He also reported the district had $1.1 million dollars in the building fund that could be used to complete some of the other projects.